In progress:

Stage 7

Estimated: Nov 2021

View Details

47%

Planning100%


Planning100%


Civil Construction46%


Site Establishment100%


Bulk Earthworks100%


Drainage Works90%


Sewer Works80%


Water & Gas Reticulation45%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Settlements0%


Close Details

Stage 8

Estimated: Mar 2022

View Details

24%

Planning100%


Planning100%


Civil Construction21%


Site Establishment100%


Bulk Earthworks80%


Drainage Works10%


Sewer Works0%


Water & Gas Reticulation0%


Subgrade Placement Works0%


Electrical & NBN0%


Footpaths/Asphalt/Linemarking0%


Practical Completion0%


Registration Progress0%


Statement of Compliance0%


Lodge Plan of Subdivision0%


Titles0%


Settlements0%


Close Details

Completed:

Stage 1

Complete: Jan 2020

Stage 2

Complete: Jan 2020

Stage 3

Complete: Jan 2020

Stage 4a

Complete: Jan 2020

Stage 4b

Complete: June 2021

Stage 5a

Complete: Aug 2020

Stage 5b

Complete: Dec 2020

Stage 6a

Complete: June 2021

Stage 6b

Complete: September 2021

Register
your interest.

Please contact us for all general community enquiries and feedback.

One of our friendly staff will be in touch with you soon.

Register Your Interest
Get:
(Choose both or one)

By continuing you are agreeing to the Privacy Policy and Disclaimer.

Marketing opt-in